KMH Engineering Inc.

KMH Provides E&I Design for Balance of Plant of New Cogeneration Plant

April 30, 2009: The scope of this project was to relocate and or duplicate approximately 100 high priority controls located in an existing Boiler House requiring integration into a new Cogeneration Facility to facilitate the operation of the existing Boiler House from the new control room. A new emergency stop panel was designed to be installed in the new control room to allow remote tripping of Boilers, Turbo Blowers, Turbines, a Praxair T-300 system and an O2 pressure reducing station. New remote drum level indicators were installed in the new control room to allow remote viewing of boiler drum levels. KMH provide construction supervision and commissioning support.